71. O on a PERT/CPM chart represents
Correct answer: (A)
an ordinary event
72. One of the basic essentials of an incentive plan is that
Correct answer: (E)
all standards should be based on time studies.
73. One time measurement unit (TMU) in method time measurement system equals
Correct answer: (B)
0.0006 minute
74. Per cent idle time for men or machines is found by
Correct answer: (A)
work sampling
75. PERT analysis is based on
Correct answer: (D)
all of the above
76. PERT and CPM are
Correct answer: (E)
aids to the decision maker.
77. PERT has following time estimate
Correct answer: (C)
three time estimate
78. PERT is
Correct answer: (E)
all of the above.
79. PERT is the
Correct answer: (B)
event oriented technique
80. PERT stands for k
Correct answer: (A)
project evaluation and review technique