Production Technology
1. 'Value' for value engineering and analysis purposes is defined as
- purchase value
- saleable value
- depreciated value
- present worth
- function/cost.
Correct answer: (E)
function/cost.
2. A big advantage of PERT over Gantt charts is that in the former case
- activities and events are clearly shown
- early start and late finish of an activity are clearly marked
- activity times are clear
- critical path can be easily determined
- inter-relationship among activities is clearly shown.
Correct answer: (E)
inter-relationship among activities is clearly shown.
3. A CPM family includes
- CPA (Critical Path Analysis)
- CPP (Critical Path Plotted)
- MCE (Minimum Cost Expenditure)
- CPS (Critical Path Scheduling)
- all of the above.
Correct answer: (E)
all of the above.
4. A dummy activity
- is artificially introduced
- is represented by a dotted line
- does not require any time
- all of the above
- none of the above.
Correct answer: (D)
all of the above
5. A low unit cost can be obtained by following
- product layout
- functional layout
- automatic material handling equipment
- specialisation of operation
- minimum travel time plan and com¬pact layout.
Correct answer: (A)
product layout
6. A milestone chart
- shows the inter dependences of various jobs
- depicts the delay of jobs, if any
- points outgoing ahead of schedule of jobs, if any
- all of the above
- none of the above.
Correct answer: (E)
none of the above.
7. ABC analysis deals with
- analysis of process chart
- flow of material
- ordering schedule of job
- controlling inventory costs money
- all of the above.
Correct answer: (D)
controlling inventory costs money
8. Acceptance sampling is widely used in
- batch production
- job production
- mass production
- all of the above
- none of the above.
Correct answer: (C)
mass production
9. According to MAPI formula, the old machine should be replaced by new one when
- CAM < DAM
- CAM > DAM
- CAM = DAM
- there is no such criterion
- none of the above.
Correct answer: (A)
CAM < DAM
10. According to Rowan plan, if H = hourly rate, A = actual time and S = standard time, then wages will be
- HA
- HA + (S˜A) HA
- HA + ˆˆ-H
- HA + ˆˆ-H
- HA + ˆˆ-HA.
Correct answer: (B)
HA + (S˜A) HA