81. PERT is the
- time oriented technique
- event oriented technique
- activity oriented technique
- target oriented technique
- work oriented technique.
Correct answer: (B)
event oriented technique
82. PERT/CPM, techniques can be used for following applications
- once through project
- maintenance jobs
- research and development
- all non-technical jobs
- all of the above.
Correct answer: (E)
all of the above.
83. Pessimistic time is
- the maximum time which an activity might require
- the average time required for a job
- the most probable time considering all conditions
- the minimum time in which an activity can possibly be accomplished
- the earliest finish.
Correct answer: (A)
the maximum time which an activity might require
84. Pick up the correct statement about relationship between various floats
- free float = total float
- independent float = total float
- independent float > free float
- free float > total float
- independent float < free float.
Correct answer: (E)
independent float < free float.
85. Pick up the correct statement from the following
- programmer evaluation and review technique is event oriented
- programmer evaluation and review technique is not event oriented
- critical path method is event oriented
- critical.path method is not activity oriented
- none of the above.
Correct answer: (E)
none of the above.
86. Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it
- consumes time, but no resources
- consumes resources but no time
- consumes neither time nor resources
- is a dangling event
- consumes both resources and time.
Correct answer: (C)
consumes neither time nor resources
87. Pick up the correct step used for scheduling a project by C.P.M.
- a project is divided into various activities
- required time for each activity is established
- sequence of various activities is made according to their importance
- network is drawn by connecting the activities and the events
- all of the above.
Correct answer: (E)
all of the above.
88. Pick up the incorrect statement about advantages of work sampling
- permits a fine breakdown of activities and delays
- simultaneous study of many operators may be made by a single observer
- calculations are easier, method is economical and less time consuming
- no time measuring devices are generally needed
- as operators are not watched for long periods, chances of obtaining misleading results are less.
Correct answer: (A)
permits a fine breakdown of activities and delays
89. Pick up the incorrect statement from the following
- an activity of the project is denoted by an arrow on the net work
- the tail of the arrow indicates the start of the activity
- the head of the arrow indicates the end of,the activity!
- the arrows are drawn (to scale from) left to right
- each activity consumes a given time
Correct answer: (D)
the arrows are drawn (to scale from) left to right
90. Pick up the incorrect statement from the following. A critical ratio scheduling
- establishes the relative priorities among various activities on a common basis
- determines the status of each activity
- adjusts automatically changes in activity progress
- is a dynamic system
- none of the above.
Correct answer: (E)
none of the above.