41. Graphical method, simplex method, and transportation method are concerned with
Correct answer: (C)
linear programming
42. If a worker gets a daily wage of Rs HA, then according to Rowan plan, his maximum daily earnings can be
Correct answer: (A)
2 HA
43. If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good
Correct answer: (E)
all of the above.
44. If TL is the largest allowable event occurrence time, total activity slack (s) is equal to
Correct answer: (D)
all of the above
45. In a PERT chart
Correct answer: (A)
all activities should be numbered
46. In A-B-C control policy, maximum attention is given to
Correct answer: (D)
those items which consume more money
47. In Halsey 50-50 plan, output standards are established
Correct answer: (B)
from previous production records
48. In inventory control, the economic order quantity is the
Correct answer: (A)
optimum lot size
49. In Lincoln plan (one type of group incentive plan), the amount of the profit which an .employee receives in addition to the guaranteed basic pay/wages, is based on:
Correct answer: (B)
a merit rating system
50. In micromotion study, therblig is described by
Correct answer: (E)
standard symbol and colour.