Production Technology

21. Choose the wrong statement Time study is used to

  1. determine overhead expenses
  2. provide a basis for setting piece prices or incentive wages
  3. determine standard costs
  4. determine the capability of an operator to handle the number of machines
  5. compare alternative methods.

Correct answer: (A)
determine overhead expenses

22. Choose the wrong statement. Motion study is used for

  1. improving a work method
  2. improvising a work method
  3. designing a work method
  4. providing a schematic framework
  5. reducing inventory costs.

Correct answer: (E)
reducing inventory costs.

23. CPM has following time estimate

  1. one time estimate
  2. two time estimate
  3. three time estimate
  4. four time estimate
  5. nil time estimate.

Correct answer: (A)
one time estimate

24. CPM is the

  1. time oriented technique
  2. event oriented technique
  3. activity oriented technique
  4. target oriented technique
  5. work oriented technique.

Correct answer: (C)
activity oriented technique

25. CPMis

  1. synthesising in concepts
  2. is built of activities oriented program-mes
  3. is, based on one time eytimate
  4. is used for repetitive works
  5. all of the above.

Correct answer: (E)
all of the above.

26. Critical path moves along the activities having total float of

  1. positive value
  2. negative value
  3. zero value
  4. same value
  5. none of the above.

Correct answer: (C)
zero value

27. Critical Path Net Work helps an engineer

  1. to concentrate his attention on critical activities
  2. to divert the resources from non-critical advanced activities to critical activities
  3. to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
  4. all of the above
  5. none of the above.

Correct answer: (D)
all of the above

28. Criticalpath on PERT/CPM chart is obtained by joining the events having

  1. maximum slack
  2. minimum slack
  3. average slack
  4. no slack
  5. judgement and experience.

Correct answer: (B)
minimum slack

29. Current assets include

  1. manufacturing plant
  2. manufacturing plant and equipment
  3. inventories
  4. common stock held by the firm
  5. all of the above.

Correct answer: (A)
manufacturing plant

30. Descripancies of bar chart techniques are

  1. consequential effects of lack in one activity on omer
  2. consequential effects of lack in one activity on the finish date
  3. free time available for an activity can't be predicted
  4. effective monitoring/controlling can't be done
  5. all of the above.

Correct answer: (E)
all of the above.

Page 3 of 18