131. The most important objective behind plant layout is
- overall simplification, safety of integration
- economy in space
- maximum travel time in plant
- to provide conveniently located shops
- to avoid any bottlenecks.
Correct answer: (A)
overall simplification, safety of integration
132. The most popular type of organisation used for Civil Engineering Constructions is
- line organisation
- line and staff organisation
- functional organisation
- effective organisation
- none of the above.
Correct answer: (A)
line organisation
133. The objective of time study is to determine the time required to complete a job by
- fast worker
- average worker
- slow worker
- new entrant
- any one of the above.
Correct answer: (B)
average worker
134. The performance of a specific task in CPM is known as
- dummy
- event
- activity
- contract
- none of the above.
Correct answer: (C)
activity
135. The probability distribution of activity times in PERT follows following distribution
- normal
- binomial
- beta
- exponential
- Gaussian.
136. The probability distribution of project completion in PERT follows following distribution
- normal
- binomial
- beta
- exponential
- Gaussian.
Correct answer: (E)
Gaussian.
137. The process layout is best suited where
- specialisation exists
- machines are arranged according to sequence of operation
- few number of non-standardised units are to be produced
- mass production is envisaged
- bought out items are more.
Correct answer: (C)
few number of non-standardised units are to be produced
138. The reasons which are basically responsible for the formation of a queue should be that
- the average service rate Hess than the average arrival rate
- output rate is linearly proportional to input
- output rate is constant and the input varies in a random manner
- all of the above
- none of the above.
Correct answer: (D)
all of the above
139. The salient feature of functional organisation is
- strict adherence to specification
- separation of planning and design part
- each individual maintains functional efficiency
- work is properly planned and distributed
- all of the above.
Correct answer: (E)
all of the above.
140. The simplex method is the basic method for
- value analysis
- operation research
- linear programming
- model analysis
- none of the above.
Correct answer: (C)
linear programming