Production Technology
111. Templates are used for
- a planning layout
- flow of material
- advancing a programme in automatic machines
- copying complicated profiles
- none of the above.
Correct answer: (A)
a planning layout
112. The allowed time for a job equals standard time plus
- policy allowance
- interference allowance
- process allowance
- learning allowance
- unforeseen allowance.
Correct answer: (A)
policy allowance
113. The amount deducted from the salary of workers towards employees provident fund is
- credited into reserves of company
- deposited in nationalised bank
- deposited in post office
- deposited in the account of worker with employer or Reserve Bank of India
- deposited in the account of worker with Provident Fund Commissioner.
Correct answer: (E)
deposited in the account of worker with Provident Fund Commissioner.
114. The appellate authority for an industrial dispute is
- management
- labour court
- high court/supreme court
- board of directors
- president.
Correct answer: (C)
high court/supreme court
115. The artificial activity; which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as
- event
- free float
- artificial
- constraint
- dummy.
Correct answer: (E)
dummy.
116. The assumption in PERT is
- a project will always be behind schedule, if left uncorrected
- cost of project will always be more than the estimated cost, if no timely corrections are taken
- a project can be subdivided into a set of predictable, independent activities
- activities are fixed and can't be changed ,
- commissioning time can be changed, if activities are behind schedule.
Correct answer: (C)
a project can be subdivided into a set of predictable, independent activities
117. The basic difference between PERT and CPM is that
- PERT deals with events and CPM with activities
- critical path is determined in PERT only
- costs are considered on CPM only and not in PERT
- guessed times are used in PERT and evaluated times in CPM
- PERT is used in workshops and CPM in plants.
Correct answer: (D)
guessed times are used in PERT and evaluated times in CPM
118. The critical activity has
- maximum float
- minimum float
- zero float,
- average float
- none of these.
Correct answer: (C)
zero float,
119. The critical path of a network represents
- the minimum time required for completion of project
- the maximum time required for completion of project
- maximum cost required for completion of project
- minimum cost required for completion of project
- none of the above.
Correct answer: (A)
the minimum time required for completion of project
120. The deductions for, employees provident fund start
- immediately on joining the service
- after 60 days of joining the service
- after 100 days of joining the service
- after 240 days of joining the service
- after one year of joining the service.
Correct answer: (D)
after 240 days of joining the service