91. Process layout is employed for
- batch production
- continuous type of product
- effective utilisation of machines
- all of the above
- none of the above.
Correct answer: (A)
batch production
92. Product layout is employed for
- batch production
- continuous production1
- effective utilization of machine
- all of the above
- none of the above.
Correct answer: (A)
batch production
93. Queuing theory deals with problems of
- material handling
- reducing the waiting time or idle Jajme
- better utilization of man services
- effective use of machines
- none of the above.
Correct answer: (B)
reducing the waiting time or idle Jajme
94. Routing prescribes the
- flow of material in the plant
- proper utilization of man power
- proper utilization of machines
- inspection of final product
- none of the above.
Correct answer: (A)
flow of material in the plant
95. Scheduling gives information about
- when work should start and how much work should be completed during a certain period
- when work should complete
- that how idle time can be minimised
- prcper utilisation of machines
- none of the above.
Correct answer: (A)
when work should start and how much work should be completed during a certain period
96. Standard time as compared to normal time is
- greater
- smaller
- equal
- there is no such correlation
- none of the above.
Correct answer: (A)
greater
97. Standard time is defined as
- normal time + allowances
- normal time + idle time + allowances
- normal time + idle time
- only normal time for an operation
- none of the above.
Correct answer: (A)
normal time + allowances
98. Standing orders which are statutory are applicable to
- all industries
- all process industries and thermal power plants
- only major industries
- only key industries
- all industries employing more than 100 workers.
Correct answer: (E)
all industries employing more than 100 workers.
99. Statistical quality control techniques are based on the theory of
- quality
- statistics
- probability
- all of the above
- none of the above.
Correct answer: (C)
probability
100. String diagram is used when
- team of workers is working at a place
- material handling is to be done
- idle time is to be reduced
- all of the above
- none of the above.
Correct answer: (A)
team of workers is working at a place