Industrial Engineering

91. Process layout is employed for

  1. batch production
  2. continuous type of product
  3. effective utilisation of machines
  4. all of the above
  5. none of the above.

Correct answer: (A)
batch production

92. Product layout is employed for

  1. batch production
  2. continuous production1
  3. effective utilization of machine
  4. all of the above
  5. none of the above.

Correct answer: (A)
batch production

93. Queuing theory deals with problems of

  1. material handling
  2. reducing the waiting time or idle Jajme
  3. better utilization of man services
  4. effective use of machines
  5. none of the above.

Correct answer: (B)
reducing the waiting time or idle Jajme

94. Routing prescribes the

  1. flow of material in the plant
  2. proper utilization of man power
  3. proper utilization of machines
  4. inspection of final product
  5. none of the above.

Correct answer: (A)
flow of material in the plant

95. Scheduling gives information about

  1. when work should start and how much work should be completed during a certain period
  2. when work should complete
  3. that how idle time can be minimised
  4. prcper utilisation of machines
  5. none of the above.

Correct answer: (A)
when work should start and how much work should be completed during a certain period

96. Standard time as compared to normal time is

  1. greater
  2. smaller
  3. equal
  4. there is no such correlation
  5. none of the above.

Correct answer: (A)
greater

97. Standard time is defined as

  1. normal time + allowances
  2. normal time + idle time + allowances
  3. normal time + idle time
  4. only normal time for an operation
  5. none of the above.

Correct answer: (A)
normal time + allowances

98. Standing orders which are statutory are applicable to

  1. all industries
  2. all process industries and thermal power plants
  3. only major industries
  4. only key industries
  5. all industries employing more than 100 workers.

Correct answer: (E)
all industries employing more than 100 workers.

99. Statistical quality control techniques are based on the theory of

  1. quality
  2. statistics
  3. probability
  4. all of the above
  5. none of the above.

Correct answer: (C)
probability

100. String diagram is used when

  1. team of workers is working at a place
  2. material handling is to be done
  3. idle time is to be reduced
  4. all of the above
  5. none of the above.

Correct answer: (A)
team of workers is working at a place

Page 10 of 14