Industrial Engineering
1. A big advantage of PERT over Gantt charts is that in the former case
- activities and events are clearly shown
- early start and late finish of an ac¬tivity are clearly marked
- activity times are clear
- critical path can be easily determined
- inter-relationship among activities is clearly shown.
Correct answer: (E)
inter-relationship among activities is clearly shown.
2. According to Rowan plan, if H = hourly rate, A = actual time and S = standard time, then wages will be
- HA
- HA + (S~A) HA
- HA + ^^-H
- HA + ^^-H
- HA + ^^-HA.
Correct answer: (B)
HA + (S~A) HA
3. An optimum project schedule implies
- optimum utilisation of men, machines and materials
- lowest possible cost and shortest possible time for project
- timely execution of project
- to produce best results under given constraints
- realistic execution time, minimum cost and maximum profits.
Correct answer: (B)
lowest possible cost and shortest possible time for project
4. Bin card is used in
- administrative wing
- workshop
- foundary shop
- stores
- assembly shop.
Correct answer: (D)
stores
5. Break-even analysis can be used for
- short run analysis
- long run analysis
- average of above two run analysis
- there is no such criterion
- none of the above.
Correct answer: (A)
short run analysis
6. CPM has following time estimate
- one time estimate
- two time estimate
- three time estimate
- four time estimate
- nil time estimate.
Correct answer: (A)
one time estimate
7. CPM is the
- time oriented technique
- event oriented technique
- activity oriented technique
- target oriented technique
- work oriented technique.
Correct answer: (C)
activity oriented technique
8. Graphical method, simplex method, and transportation method are concerned with
- break-even analysis
- value analysis
- linear programming
- queing theory
- tnaterial handling.
Correct answer: (C)
linear programming
9. If a worker gets a daily wage of Rs HA, then according to Rowan plan, his maximum daily earnings can be
- 2 HA
- 1.33 HA
- 1.5 HA
- 1.15 HA
- 2.5 HA.
10. In A-B-C control policy, maximum attention is given to
- those items which consume money
- those items which are not readily available
- thosex items which are in more demand
- those items which consume more money
- proper quality assurance program-mes.
Correct answer: (D)
those items which consume more money