61. The most reliable estimate is

  1. Detailed estimate
  2. Preliminary estimate
  3. Plinth area estimate
  4. Cube rate estimate

Correct answer: (A)
Detailed estimate

62. The order of booking dimensions is

  1. Length, breadth, height
  2. Breadth, length, height
  3. Height, breadth, length
  4. None of these

Correct answer: (A)
Length, breadth, height

63. The plinth area of a building not includes

  1. Area of the walls at the floor level
  2. Internal shaft for sanitary installations up to 2 sq m. in area
  3. Lift and wall including landing
  4. Area of cantilevered porch

Correct answer: (D)
Area of cantilevered porch

64. The rate of an item of work depends on

  1. Specifications of works
  2. Specifications of materials
  3. Proportion of mortar
  4. All the above

Correct answer: (D)
All the above

65. The rate of payment is made for 100 cu m (per % cu m) in case of

  1. Earth work in excavation
  2. Rock cutting
  3. Excavation in trenches for foundation
  4. All the above

Correct answer: (D)
All the above

66. The slope of the outlet of 'P trap' below the horizontal is kept

  1. 10°
  2. 12°
  3. 14°

Correct answer: (D)
14°

67. The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective length L, is

  1. L + 0.42 d
  2. L + (2 × 0.42 d)
  3. L - (0.42 d)
  4. L - (2 × 0.4 d)

Correct answer: (B)
L + (2 × 0.42 d)

68. The trap which is provided to disconnect the house drain from the street sewer is called

  1. Master trap
  2. Intercepting trap
  3. Interception manhole
  4. All the above

Correct answer: (D)
All the above

69. The unit of measurement is per quintal for the following:

  1. Collapsible gates with rails
  2. Rolling shutters
  3. Expanded metal wire netting
  4. M.S. reinforcement of R.C.C. works

Correct answer: (D)
M.S. reinforcement of R.C.C. works

70. The volume is measured correct to the nearest

  1. 0.01 cum
  2. 0.02 cum
  3. 0.03 cum
  4. 0.04 cum

Correct answer: (A)
0.01 cum