1. A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is
Correct answer: (C)
1500 m3
2. A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved.
Correct answer: (D)
27,500 m3
3. According to Indian Standards Institute, the actual size of modular bricks is
Correct answer: (C)
19 cm × 9 cm × 9 cm
4. According to ISI method of measurement, the order of the sequence is
Correct answer: (A)
Length, breadth, height
5. Anti-siphonage pipe is connected to
Correct answer: (C)
Top of P trap W.C.
6. As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken
Correct answer: (D)
All the above
7. Berms are provided in canals if these are
Correct answer: (B)
Partly in excavation and partly in embankment
8. Brick walls are measured in sq. m if the thickness of the wall is
Correct answer: (A)
10 cm
9. Carpet area does not include the area of
Correct answer: (D)
All the above
10. Cost of fittings and their fixing is specified for the following sanitary fittings
Correct answer: (D)
All the above