Docks and Harbour Engineering
51. Pick up the incorrect statement from the following:
- As a wave of sea water approaches the coast line, it is generally accompanied by a drift of water in the direction of wave advance
- The on-shore wind helps to produce wave action as well as rise of M.S.L.
- A falling hydraulic gradient occurs in the direction of the wave
- The wave while receding carries finer particles out to deep water
Correct answer: (C)
A falling hydraulic gradient occurs in the direction of the wave
52. Pick up the incorrect statement from the following: In a dry dock block made of hard wood,
- Spacing of the blocks is 1.35 m
- The lowest block is 1.8 m long 40 cm × 40 cm in cross-section
- The middle block is 1.6 m long 40 cm × 40 cm in cross-section
- None of these
Correct answer: (D)
None of these
53. Select the incorrect statement.
- The progress of work in low level method of mound construction is very slow
- Barge method of mound construction is economical
- In low level method of mound construction, the area of working is limited
- In staging method of mound construction, the work is not interrupted even during stormy weather
Correct answer: (B)
Barge method of mound construction is economical
54. Soundings are required for
- Making nautical charts for navigation
- Ascertaining the areas subject to scour or silting
- Obtaining detailed information for construction
- All the above
Correct answer: (D)
All the above
55. The beach is built:
- With largest material locally available to the waves
- With large material locally available to the waves
- With fine material locally available to the waves
- With finest material locally available to the waves
Correct answer: (A)
With largest material locally available to the waves
56. The difference in height between highest high water and lowest low water is called
- Mean range
- Maximum range
- Maximum rise
- Mean rise
Correct answer: (B)
Maximum range
57. The dock wall is designed as a gravity retaining wall and is tested for
- Back fill pressure when the dock is empty
- Maximum water pressure from the dock without any back fill
- The load charge transmitted to the dock by the movement of loaded vehicles or trains on the way
- All of the above
Correct answer: (D)
All of the above
58. The fixed mooring does not require
- Mooring post
- Bollard
- Anchors
- Capstan
Correct answer: (C)
Anchors
59. The floating mooring does not require
- Cables
- Anchors
- Bollard
- Buoy
Correct answer: (C)
Bollard
60. The heaviest line is used to democrat
- The low water line
- The high water line
- The limit of swamps
- The direction of current
Correct answer: (B)
The high water line