Construction Planning and Management

131. The time with which direct cost does not reduce with the increase in time is known as

  1. Crash time
  2. Normal time
  3. Optimistic time
  4. Standard time

Correct answer: (B)
Normal time

132. Time and progress chart of a construction, is also known as

  1. Bar chart
  2. Gantt chart
  3. Modified Mile stone chart
  4. All the above

Correct answer: (D)
All the above

133. Total float for any activity is defined as the difference between

  1. Its latest finish time and earliest start time for its successor activity
  2. Its latest start time and earliest start time
  3. Its latest start time and earliest finish time
  4. Its earliest finish time and earliest start time for its successor activity

Correct answer: (B)
Its latest start time and earliest start time

134. Updating may result in

  1. Change of critical path
  2. Decrease of project completion time
  3. Increase of project completion time
  4. All of the above

Correct answer: (D)
All of the above

135. Various activities of a project, are shown on bar charts by

  1. Vertical lines
  2. Horizontal lines
  3. Dots
  4. Crosses

Correct answer: (B)
Horizontal lines

136. Whenever an activity has zero total float, then

  1. Free float of the activity must be zero but independent float need not be zero
  2. Independent float must be zero but free float need not be zero
  3. Free float and independent float both must be zero
  4. Free float and independent float both need not be zero

Correct answer: (C)
Free float and independent float both must be zero

137. Which of the following does not represent an activity?

  1. Site located
  2. Foundation is being dug
  3. The office area is being cleaned
  4. The invitations are being sent

Correct answer: (A)
Site located

138. Which of the following earth moving machines has the shortest cycle time?

  1. Drag line
  2. Hoe
  3. Clam shell
  4. Dipper shovel

Correct answer: (D)
Dipper shovel

139. Which of the following excavators is most suitable for digging under water?

  1. Drag line
  2. Hoe
  3. Clam shell
  4. Dipper shovel

Correct answer: (A)
Drag line

140. Which of the following is a weakness of bar chart?

  1. Interdependencies of activities
  2. Project progress
  3. Uncertainties
  4. All of the above

Correct answer: (D)
All of the above

Page 14 of 15