Construction Planning and Management
131. The time with which direct cost does not reduce with the increase in time is known as
- Crash time
- Normal time
- Optimistic time
- Standard time
Correct answer: (B)
Normal time
132. Time and progress chart of a construction, is also known as
- Bar chart
- Gantt chart
- Modified Mile stone chart
- All the above
Correct answer: (D)
All the above
133. Total float for any activity is defined as the difference between
- Its latest finish time and earliest start time for its successor activity
- Its latest start time and earliest start time
- Its latest start time and earliest finish time
- Its earliest finish time and earliest start time for its successor activity
Correct answer: (B)
Its latest start time and earliest start time
134. Updating may result in
- Change of critical path
- Decrease of project completion time
- Increase of project completion time
- All of the above
Correct answer: (D)
All of the above
135. Various activities of a project, are shown on bar charts by
- Vertical lines
- Horizontal lines
- Dots
- Crosses
Correct answer: (B)
Horizontal lines
136. Whenever an activity has zero total float, then
- Free float of the activity must be zero but independent float need not be zero
- Independent float must be zero but free float need not be zero
- Free float and independent float both must be zero
- Free float and independent float both need not be zero
Correct answer: (C)
Free float and independent float both must be zero
137. Which of the following does not represent an activity?
- Site located
- Foundation is being dug
- The office area is being cleaned
- The invitations are being sent
Correct answer: (A)
Site located
138. Which of the following earth moving machines has the shortest cycle time?
- Drag line
- Hoe
- Clam shell
- Dipper shovel
Correct answer: (D)
Dipper shovel
139. Which of the following excavators is most suitable for digging under water?
- Drag line
- Hoe
- Clam shell
- Dipper shovel
Correct answer: (A)
Drag line
140. Which of the following is a weakness of bar chart?
- Interdependencies of activities
- Project progress
- Uncertainties
- All of the above
Correct answer: (D)
All of the above