Construction Planning and Management

121. The probability of completion of any activity within its expected time is

  1. 0.5
  2. 0.841
  3. 0.999
  4. 1

Correct answer: (A)
0.5

122. The process of incorporating changes and rescheduling or replanning is called

  1. Resource levelling
  2. Resource smoothening
  3. Updating
  4. Critical path scheduling

Correct answer: (C)
Updating

123. The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawlermounted and pneumatic tyre-mounted machines would be respectively

  1. 80 and 90
  2. 90 and 80
  3. 85 and 75
  4. 75 and 83

Correct answer: (D)
75 and 83

124. The reduction in project time normally results in

  1. Decreasing the direct cost and increasing indirect cost
  2. Increasing the direct cost and decreasing the indirect cost
  3. Increasing the direct cost and indirect cost both
  4. Decreasing the direct cost and indirect cost both

Correct answer: (B)
Increasing the direct cost and decreasing the indirect cost

125. The salient feature of functional organisation is

  1. Strict adherence to specifications
  2. Separation of planning and design part
  3. Each individual maintains functional efficiency
  4. All the above

Correct answer: (D)
All the above

126. The technique for establishing and maintaining priorities among the various jobs of a project, is known

  1. Event flow scheduling technique
  2. Critical ratio scheduling
  3. Slotting technique for scheduling
  4. Short interval scheduling

Correct answer: (B)
Critical ratio scheduling

127. The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as

  1. Total float
  2. Free float
  3. Interfering float
  4. Independent float

Correct answer: (D)
Independent float

128. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as

  1. Duration
  2. Total float
  3. Free float
  4. Interfering float

Correct answer: (C)
Free float

129. The time corresponding to minimum total project cost is

  1. Crash time
  2. Normal time
  3. Optimistic time
  4. Between normal time and crash time

Correct answer: (D)
Between normal time and crash time

130. The time which results in the leasi, possible construction cost of an activity, is known as

  1. Normal time
  2. Slow time
  3. Crash time
  4. Standard time

Correct answer: (B)
Slow time