121. The probability of completion of any activity within its expected time is
Correct answer: (A)
0.5
122. The process of incorporating changes and rescheduling or replanning is called
Correct answer: (C)
Updating
123. The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawlermounted and pneumatic tyre-mounted machines would be respectively
Correct answer: (D)
75 and 83
124. The reduction in project time normally results in
Correct answer: (B)
Increasing the direct cost and decreasing the indirect cost
125. The salient feature of functional organisation is
Correct answer: (D)
All the above
126. The technique for establishing and maintaining priorities among the various jobs of a project, is known
Correct answer: (B)
Critical ratio scheduling
127. The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
Correct answer: (D)
Independent float
128. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
Correct answer: (C)
Free float
129. The time corresponding to minimum total project cost is
Correct answer: (D)
Between normal time and crash time
130. The time which results in the leasi, possible construction cost of an activity, is known as
Correct answer: (B)
Slow time