Construction Planning and Management

101. The critical activity has

  1. Maximum float
  2. Minimum float
  3. Zero float
  4. None of these

Correct answer: (C)
Zero float

102. The difference between the time avail-to do a job and the time required to do the job, is known as

  1. Event
  2. Float
  3. Duration
  4. Constraint

Correct answer: (B)
Float

103. The direct cost of a project with respect to normal time is

  1. minimum
  2. Maximum
  3. Zero
  4. Infinite

Correct answer: (A)
minimum

104. The estimated time required to perform an activity, is known as

  1. Event
  2. Dummy
  3. Duration
  4. Float

Correct answer: (C)
Duration

105. The final selection of a construction site, is done by

  1. Departmental representative or user
  2. Local civil authority representative
  3. Representative of engineer authority
  4. All the above

Correct answer: (D)
All the above

106. The first method invented for planning projects, was

  1. Bar chart method
  2. Milestone chart
  3. Critical path method (CPM)
  4. Programme Evaluation and Review Technique (PERT)

Correct answer: (A)
Bar chart method

107. The first stage of a construction, is

  1. Preparation of estimate
  2. Survey of the site
  3. Initiation of proposal
  4. Preparation of tender

Correct answer: (C)
Initiation of proposal

108. The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to

  1. 2 kg/tonne
  2. 6 kg/tonne
  3. 9 kg/tonne
  4. 20 kg/tonne

Correct answer: (C)
9 kg/tonne

109. The independent float affects only

  1. Preceding activities
  2. Succeeding activities
  3. The particular activity involved
  4. None of the above

Correct answer: (C)
The particular activity involved

110. The main advantage of line organisation is:

  1. Effective command and control
  2. Rigid discipline in the organisation
  3. Defined responsibilities at all levels
  4. All the above

Correct answer: (D)
All the above