101. The critical activity has
Correct answer: (C)
Zero float
102. The difference between the time avail-to do a job and the time required to do the job, is known as
Correct answer: (B)
Float
103. The direct cost of a project with respect to normal time is
Correct answer: (A)
minimum
104. The estimated time required to perform an activity, is known as
Correct answer: (C)
Duration
105. The final selection of a construction site, is done by
Correct answer: (D)
All the above
106. The first method invented for planning projects, was
Correct answer: (A)
Bar chart method
107. The first stage of a construction, is
Correct answer: (C)
Initiation of proposal
108. The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to
Correct answer: (C)
9 kg/tonne
109. The independent float affects only
Correct answer: (C)
The particular activity involved
110. The main advantage of line organisation is:
Correct answer: (D)
All the above