Construction Planning and Management
91. Select the correct statement.
- Activity arrows in a CPM network are drawn to scale
- The tail of an arrow represents the finish of an activity
- Arrow bead represents the start of an activity
- None of the above
Correct answer: (D)
None of the above
92. Select the incorrect statement.
- Start float and finish float are always equal.
- Total float can be either start float or finish float.
- Start float and finish float need not be equal.
- Start float and finish float are the differences between activity times and not event times.
Correct answer: (C)
Start float and finish float need not be equal.
93. Sensitivity analysis is a study of
- Comparison of profit and loss
- Comparison of assets and liabilities
- Change in output due to change in input
- Economics of cost and benefits of the project
Correct answer: (C)
Change in output due to change in input
94. Sinking fund is
- The fund for rebuilding a structure when its economic life is over
- Raised to meet maintenance costs
- The total sum to be paid to the municipal authorities by the tenants
- A part of the money kept in reserve for providing additional structures and structural modifications
Correct answer: (A)
The fund for rebuilding a structure when its economic life is over
95. Site order book is used for recording
- Instructions by the executive engineers
- Construction measurements
- Issue of store equipments
- Names of the casual labour
Correct answer: (A)
Instructions by the executive engineers
96. Slack time refers to
- An activity
- An event
- Both event and activity
- None of the above
Correct answer: (B)
An event
97. The area under the Beta distribution curve is divided into two equal parts by
- Most likely time
- Optimistic time
- Pessimistic time
- Expected time
Correct answer: (D)
Expected time
98. The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as
- Event
- Free float
- Dummy
- Constraint
99. The basic action involved in sheep foot rolling is
- Kneading
- Pressing
- Tamping
- Vibration
Correct answer: (A)
Kneading
100. The constraints in case of resource smoothening operation would be
- Resources
- Project duration time
- Both resources and project duration time
- None of the above
Correct answer: (B)
Project duration time