1. A construction schedule is prepared after collecting
Correct answer: (D)
All the above
2. A CPM family includes
Correct answer: (D)
All the above
3. A critical ratio scheduling
Correct answer: (D)
None of these
4. A dummy activity
Correct answer: (D)
All the above
5. A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be
Correct answer: (C)
40 kg/tonne
6. A golden rule for the procurement of construction stones, suggests
Correct answer: (B)
67% at the site and 33% under procurement
7. A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be
Correct answer: (B)
Rs. 3480
8. A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is
Correct answer: (B)
Rs. 5,75,000
9. A Milestone chart
Correct answer: (D)
None of these
10. A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be
Correct answer: (B)
4.23 years