Building Construction

71. In English garden wall bond

  1. One course of headers to three or five course of stretchers
  2. Queen closer in provided in each heading course
  3. The middle course of stretchers is started with a header to give proper vertical joints
  4. All the above

Correct answer: (D)
All the above

72. In flat roof of reinforced cement concrete, the recommended angle of slope, is

  1. Zero
  2. A few degrees
  3. 10°
  4. 200°

Correct answer: (B)
A few degrees

73. In grillage foundations a minimum 15 cm cover is provided on

  1. Upper flange of top tier
  2. Lower beam of lower tier
  3. Ends of external beams
  4. None to these

Correct answer: (B)
Lower beam of lower tier

74. In grillage foundations, distance between flanges of grillage beams, is kept

  1. 40 cm
  2. Equal to flange width
  3. Twice the flange width
  4. Maximum of (a), (b) and (c)

Correct answer: (C)
Twice the flange width

75. In high mountainous region, the type of roof generally recommended for buildings, is

  1. Shed type
  2. Gable type
  3. Gambrel type
  4. Mansard type

Correct answer: (C)
Gambrel type

76. In horizontal D.P.C, thickness of cement concrete (1 : 2 : 4) is

  1. 2 cm
  2. 4 cm
  3. 6 cm
  4. 8 cm

Correct answer: (B)
4 cm

77. In jack arch floor, the rise is kept

  1. 1/6th of the span
  2. 1/8th of the span
  3. 1/10th of the span
  4. 1/12th of the span

Correct answer: (D)
1/12th of the span

78. In ordinary residential and public buildings, the damp proof course is generally provided at

  1. Ground level
  2. Plinth level
  3. Water table level
  4. Midway ground level and water-table level

Correct answer: (B)
Plinth level

79. In places where the soil is soft and has small resistance to the flow of concrete, which one of the following types of piles, is used

  1. Vibro pile
  2. Pressure pile
  3. Franki pile
  4. Pedestal pile

Correct answer: (A)
Vibro pile

80. In soft clay of low bearing capacity, the type of steel pile generally used, is

  1. H-pile
  2. Screw pile
  3. Disc pile
  4. Pipe pile

Correct answer: (B)
Screw pile

Page 8 of 28