Building Construction

191. The number of steps in a flight generally should not be less than

  1. 2
  2. 3
  3. 5
  4. No limit

Correct answer: (B)
3

192. The opening provided in sloping roof with its top parallel to the roof surface, is called

  1. Dormer window
  2. Sky light window
  3. Lantern window
  4. Louvered window

Correct answer: (B)
Sky light window

193. The piece of a brick cut along the centre of width in such a way that its length is equal to that of full brick, is called

  1. Half brick
  2. Queen closer
  3. King closer
  4. Bevelled closer

Correct answer: (B)
Queen closer

194. The piece of a brick cut with its one corner equivalent to half the length and half the width of a full brick, is known as

  1. Queen closer
  2. Bevelled closer
  3. King closer
  4. Half king closer

Correct answer: (C)
King closer

195. The pile provided with one or more bulles in its vertical shaft, is generally known as

  1. Under-ream pile
  2. Friction pile
  3. Bearing pile
  4. Sheet pile

Correct answer: (A)
Under-ream pile

196. The pile which is provided with a bulb filled with concrete at its lower end, is known as

  1. Simplex pile
  2. Mac-Arthur pile
  3. Raymond pile
  4. Franki pile

Correct answer: (B)
Mac-Arthur pile

197. The pile which supports the load due to friction between pile face and surrounding soil, is generally known as

  1. Bearing pile
  2. Friction pile
  3. Sheet pile
  4. Battered pile

Correct answer: (B)
Friction pile

198. The pile which supports the load partly by friction and partly by resting on hard stratum, is called

  1. Friction pile
  2. Bearing pile
  3. Friction bearing pile
  4. Rough pile

Correct answer: (C)
Friction bearing pile

199. The platform at the end of a series of steps, is known as

  1. Platform
  2. Relief
  3. Rest
  4. Landing

Correct answer: (D)
Landing

200. The portion of a brick cut across the width, is called

  1. Closer
  2. Half brick
  3. Bed
  4. Bat

Correct answer: (D)
Bat

Page 20 of 28